打擊式鋼版樁減震工法
國立高雄應用科技大學
2011/04/21
本發明係一種打擊式鋼版樁減震工法。 其步驟包括先於選定之地下擋土開挖施工區域內開挖減震井,該減震井挖掘高度小於該區域土壤的垂直開挖臨界高度,接著將該減震井注滿水,並將數個鋼版樁沿著該減震井周面依序排列扣接並打入地層中,以發揮擋土功能,且該些鋼版樁在地表面與土壤不接觸,打完樁後,利用抽水機將該減震井內的水抽出。 本發明利用減震井中的水有效吸收打樁過程中所產生的部分振動波,使得傳遞至鄰房的振動波較少,故波的振幅較小,波速亦減慢,使得打擊式鋼版樁所產生的振動波速小於損鄰波速,以確保鄰房的安全,並使打擊式鋼版樁施工適用的範圍更廣。 The shock absorber construction method of the present invention is a fight against the steel version pile. Steps prior to the selected underground retaining excavation Excavation shock absorption well within the construction area, the damping well mining height is less than the critical height of the region of the vertical soil excavation, and then the the damping wells filled with water, and several steel version of piles arranged in sequence along the damping wells Facial Snap and into the formation to play a retaining function, and do not touch the steel version piles on the ground surface and soil, kick down the piles after using pump water out of the shock absorption wells.
技術服務組
(07)3814526-12721
版權所有 © 國家科學及技術委員會 National Science and Technology Council All Rights Reserved.
建議使用IE 11或以上版本瀏覽器,最佳瀏覽解析度為1024x768以上|政府網站資料開放宣告
主辦單位:國家科學及技術委員會 執行單位:台灣經濟研究院 網站維護:台灣經濟研究院